Tag: downtime reduction

  • Root Cause Analysis: Using the 5 Whys and Fishbone Diagram on a Line Stoppage

    Root Cause Analysis: Using the 5 Whys and Fishbone Diagram on a Line Stoppage

    The Fault That Keeps Coming Back

    Every plant has one. A fault that stops the line, gets fixed, and returns a week later. Each time it is repaired promptly and each time the repair is logged as successful. Over a year it costs more production than any single major breakdown, and nobody has ever sat down to find out why it happens.

    Root cause analysis is the discipline of asking that question properly. This guide covers the two most widely used techniques, the 5 Whys and the fishbone diagram, with a worked example from a filling line, and explains how to make the findings stick.

    What Root Cause Analysis Is

    Root cause analysis is a structured way of working back from a problem to the underlying reason it occurred, so that the fix prevents it recurring. It rests on a distinction between three things.

    The symptom is what you see: the filler stopped on a low level alarm.

    The direct cause is the immediate technical reason: a valve was slow to open.

    The root cause is the reason the direct cause was able to happen: usually a gap in a system, such as maintenance, design, training or documentation.

    Repairs address direct causes. Root cause analysis addresses the gap. If you stop at the direct cause you will be back.

    The 5 Whys

    The 5 Whys is the simplest technique and the one most plants should start with. It came out of the Toyota production system. You state the problem and ask why it happened. You take the answer and ask why again, and continue until you reach a cause that, if corrected, would prevent the problem.

    Five is a guide and not a rule. Some problems resolve in three steps and some take seven. The signal that you have gone far enough is that the answer describes something the organisation controls and can change.

    A Worked Example From a Filling Line

    A can filler has stopped on a low bowl level fault eleven times in a month. Each stop lasted between ten and forty minutes. Each time, maintenance reset the fault and the line restarted.

    Why did the filler stop? The product level in the bowl fell below the minimum.

    Why did the level fall? The product supply valve was slow to open when the level control called for it.

    Why was the valve slow? Its pneumatic actuator was not getting enough air.

    Why was it short of air? A filter on the air line to that valve was partly blocked.

    Why was the filter blocked? It had never been changed. It was added during a modification three years earlier and was never put on the maintenance schedule or shown on the drawings.

    The direct cause is a blocked filter, fixed in ten minutes. The root cause is that modifications to the line were not being captured in the drawings and the maintenance system. Fixing that prevents this fault and an unknown number of others. The obvious next question is what else was added in that modification.

    Where the 5 Whys Falls Short

    The technique follows a single chain of cause and effect. Real problems often have several contributing causes, and a 5 Whys done by one person tends to follow whichever path that person already suspected. It can also stop too early, at an answer like operator error, which is almost never a root cause. If a person made a mistake, ask why the system made that mistake easy.

    For problems with more than one plausible cause, a wider tool is needed first.

    Fishbone Diagram

    The Fishbone Diagram

    The fishbone diagram, also called an Ishikawa diagram after the Japanese engineer Kaoru Ishikawa, or a cause and effect diagram, is a way of laying out all the possible causes of a problem before deciding which to pursue. The problem is written at the head of the fish. Bones branch off for each category of cause, and the team adds possible causes under each.

    In manufacturing the usual categories are six.

    People. Training, experience, fatigue, staffing, handover between shifts.

    Machine. Wear, settings, maintenance condition, design limitations, modifications.

    Method. Procedures, changeover practice, cleaning routines, work instructions.

    Material. Product, packaging, suppliers, batch variation.

    Measurement. Sensors, calibration, inspection methods, the data itself.

    Environment. Temperature, humidity, washdown, dust, lighting.

    The value is breadth. A team that is convinced a fault is electrical will, when made to fill in the material bone, remember that the problem started when the label supplier changed.

    Using the Two Together

    The techniques complement each other. Use a fishbone to open the question up and collect every credible cause. Use evidence to rule causes in or out, since most can be eliminated quickly with data you already hold. Then run a 5 Whys on each cause that survives.

    For the filler example, a fishbone might have raised air supply, valve wear, level sensor drift, a change in product viscosity and a control setting altered after a software change. Checking the air pressure at the valve would have pointed to the first within the hour.

    Running a Session That Works

    Pick the right problems. Root cause analysis takes time. Reserve it for faults that are expensive, repeated or dangerous. A simple trigger works well: any fault that occurs three times, any stop over a set duration and any safety incident.

    Get the right people. The operator who saw it, the tradesperson who fixed it and someone who understands the control system. Three or four people is enough.

    Go and look. Hold the session at the machine where possible. Assumptions made in a meeting room are often wrong.

    Use evidence. Alarm histories, drive fault logs, trends, maintenance records and the failed part itself. Every why should be supported by something you can point to.

    Keep blame out of it. People stop telling the truth when the exercise is about fault. The question is always what allowed this, never who did it.

    Write it down. One page: the problem, the chain of causes, the evidence, the actions, an owner and a date for each.

    From Cause to Corrective Action

    An analysis is only as good as the action that follows. Weak actions are reminders, retraining and instructions to be more careful. Strong actions change the system: a design change that removes the failure, a maintenance task added with a frequency, a drawing corrected, a spare part stocked, a setting locked.

    Then check that it worked. Set a date to review whether the fault has recurred. If it has, the root cause was not found and the analysis should be reopened without embarrassment. That is how the method is supposed to work.

    Common Root Causes in Production Plants

    Across many investigations the same themes recur. Modifications that were never documented. Maintenance tasks that exist on paper and are skipped under production pressure. Settings changed to work around a problem and never restored. Spare parts that are near enough but not identical. Sensors positioned where washdown or product build up defeats them. Knowledge held by one person and lost when they changed shift or left.

    None of these is exotic. That is the encouraging part: most root causes are within a plant’s power to fix.

    Where BevTech Fits

    BevTech is a family owned engineering business in Richlands, Brisbane, with more than 25 years in beverage and FMCG manufacturing. Our industrial electricians, automation engineers and mechanical trades are often called to the faults that keep coming back, and because all three disciplines and a machine shop sit in the same business, we can follow a cause wherever it leads, from a line of PLC logic to a worn change part. We also produce the as-built drawings and documentation that stop undocumented modifications becoming next year’s mystery.

    If your plant has a recurring fault that nobody has had time to get to the bottom of, use the contact form at bevtech.com.au/contact.

  • Electrical Fault Finding on Production Lines: A Method That Shortens Downtime

    Electrical Fault Finding on Production Lines: A Method That Shortens Downtime

    Why Some Breakdowns Take Twenty Minutes and Others Take a Shift

    Two production lines stop with the same symptom. On one, the electrician has the line running again in twenty minutes. On the other, six hours and four replaced components later, the fault is still there. The difference is rarely luck and rarely the size of the toolbox. It is method, and it is how well the plant has prepared for the day something fails.

    This guide describes how experienced industrial electricians approach electrical fault finding on production equipment, what the rules in Queensland say about testing live equipment, and what a plant can do in advance to make every fault faster to find.

    Step One: Understand the Symptom

    Good fault finding starts with questions, not a multimeter. What exactly stopped? What was the machine doing at the time? Was there an alarm, and what did it say? Has it happened before, and when? What changed recently: a product changeover, a washdown, a repair, a software edit?

    The operator who was standing there usually holds half the answer. An electrician who walks past the operator to open a panel has already lost time. The most useful habit a plant can build is to have operators write down the alarm text and the time before anyone presses reset.

    Step Two: Read What the Machine Is Telling You

    Modern equipment is generous with information. The HMI alarm history shows what tripped and in what order. Variable speed drives store fault codes with the conditions at the moment of the trip. Safety relays and safety controllers show which channel opened. The PLC itself shows the live state of every input and output.

    The first alarm in the sequence is usually the one that matters. The dozen that follow are consequences. An electrician who can go online with the controller can see in seconds which condition is preventing the machine from running, where an electrician without the software can only guess.

    Step Three: Narrow It Down Logically

    Every control circuit is a chain: a sensor, a cable, an input, logic, an output, a cable and a device. The fault is somewhere in that chain. The efficient approach is to test at the midpoint and discard the half that is working, then repeat. Three or four well chosen tests will isolate a fault that could take thirty random ones.

    Start with the simple and likely causes. Sensors that have been knocked out of position, connectors loosened by vibration, cables damaged where they flex, water in a junction box after washdown and blown fuses account for a large share of production faults. Failed PLC hardware is far less common than people assume.

    Step Four: Prove It Before You Replace It

    Swapping parts until the fault disappears is the most expensive form of fault finding. It consumes spares, it can introduce new faults, and when the machine finally runs nobody knows which change fixed it. Worse, a part that was not faulty goes back on the shelf marked as suspect.

    The discipline is to form a theory, test it, and only then replace the component. If a new sensor fixes the problem, find out why the old one failed. A sensor destroyed by a misaligned guide rail will be destroyed again next week.

    Intermittent Faults

    The hardest faults are the ones that are not present when the electrician arrives. They demand patience and evidence. Useful techniques include trending the suspect signal in the PLC, adding a temporary latch in the logic to capture a momentary drop, logging drive data, and checking whether the fault correlates with heat, vibration, a particular product or a particular time of day.

    Thermal expansion, cables that fail only when a machine is at one end of its travel and electrical noise from a nearby drive are common culprits. With intermittent faults the plant’s records matter more than anything the electrician brings.

    What Queensland Law Says About Testing Live Equipment

    Fault finding often requires measurements on energised circuits, and this is an area where the rules are strict. In Queensland, electrical work on or near energised electrical equipment is generally prohibited. Near means within 3 metres of an exposed energised part.

    Energised work is permitted only in prescribed circumstances, which include testing and situations where there is no reasonable alternative. When it is carried out, the requirements include a risk assessment, a safe work method statement, the use of suitable testing equipment and protective equipment by a competent person, keeping unauthorised people out of the immediate area and consultation with the person who manages or controls the workplace. A safety observer is required unless the work is testing only and the risk assessment shows there is no serious risk.

    For a plant manager this has two practical consequences. First, expect a competent electrician to isolate wherever testing can be done dead, and to take a few minutes over paperwork when it cannot. Second, your site is part of the process. The electrician must consult you, and the pressure to get the line back must not become pressure to skip the controls.

    Reset or Repair

    A reset restores production. A repair removes the cause. Both have their place, because sometimes the right decision is to run until the next planned stop. The mistake is to reset and forget.

    A simple rule works well. Any fault that is reset without a known cause gets written down. Any fault that appears three times gets investigated properly at the next opportunity, with the machine stopped and the time to do it. The list of repeat resets is often the best source of items for a maintenance day or a shutdown.

    What the Plant Can Do in Advance

    Most of the time lost in a breakdown is lost before the fault finding starts. These are the preparations that pay back most.

    Current drawings. Schematics that match the panel, kept where they can be found at night. This is the single biggest factor in fault finding time.

    Software backups. A current copy of every PLC, HMI and drive configuration, stored on site and off it, with the passwords.

    Labelling. Devices, cables and terminals labelled to match the drawings.

    Critical spares. The specific sensors, drives, contactors and power supplies your lines depend on, identified in advance and held where the night shift can reach them.

    A fault log. Date, machine, symptom, cause and fix. After a year it becomes the most useful document in the maintenance office.

    Operator notes. Alarm text and time recorded before reset.

    When to Call for Help

    In-house teams handle most faults well. The time to call for support is when a fault has outlasted the people on shift, when it involves a control platform nobody on site can go online with, when a safety circuit is implicated, or when the same fault keeps returning. Calling early is cheaper than calling after four hours of lost production.

    Fault Finding Support From BevTech

    BevTech is a family owned engineering business in Richlands, Brisbane, with more than 25 years in beverage and FMCG manufacturing. Our industrial electricians provide fast, methodical diagnosis of electrical and control faults during production, working on Allen Bradley and Siemens platforms across fillers, seamers, cappers, labellers, conveyors and CIP systems. We offer 24/7 breakdown support and shift coverage across Brisbane and South East Queensland, and because our mechanical trades and machine shop are part of the same business, a fault that turns out to be mechanical is still our problem to solve.

    If recurring faults are costing you production, use the contact form at bevtech.com.au/contact and we will arrange a time to look at the line.

    This article is a general guide current as at October 2026. Confirm the requirements for energised work at your own site with the Electrical Safety Office.

  • Reducing Downtime with Reliable Shift Cover: Lessons from the Beverage Production Floor

    Reducing Downtime with Reliable Shift Cover: Lessons from the Beverage Production Floor

    Downtime Is a Shift Level Problem

    Ask a plant manager about downtime and the conversation usually goes straight to big themes: reliability programmes, capital replacement, spare parts strategy. All of it matters. But watch where downtime actually accumulates on a beverage line and a humbler truth emerges. Downtime is won or lost one shift at a time, in the minutes between a fault appearing and a competent person resolving it. A plant can have a world class maintenance strategy on paper and still bleed hours every week because, on too many shifts, the right skills simply were not in the building.

    This article draws together the practical lessons from beverage and FMCG production floors about the relationship between shift cover and downtime, and how Queensland manufacturers are using reliable cover as a genuine reliability tool rather than a staffing patch.

    Lesson One: Response Time Beats Almost Everything

    The anatomy of a breakdown has three phases: time to respond, time to diagnose, time to repair. Reliability engineering obsesses over preventing the breakdown, and rightly so, but for the failures that still occur, total downtime is dominated by the first two phases. A conveyor jam that takes eight minutes to clear costs an hour if nobody qualified reaches it for fifty minutes. On uncovered shifts, response time is not measured in minutes at all; it is measured in the hours until the next crewed shift starts, or until a fatigued callout arrives from across town.

    Guaranteeing that every operating shift has competent trades cover is, hour for hour, one of the most effective downtime investments a plant can make. It attacks the largest and most controllable component of every incident.

    Lesson Two: Diagnosis Quality Determines Repeat Failures

    The second lesson is subtler. What happens during a night shift breakdown determines whether the same breakdown happens again next week. A skilled tradesperson does not just restart the line; they identify the root cause, or at least capture the evidence, fault codes, observations, part condition, that lets day shift engineering close it out properly. An unskilled stopgap gets the line moving with the mechanical equivalent of a reboot and leaves nothing behind but a vague logbook entry. The fault returns, and the plant records it as bad luck.

    This is why the quality of shift cover compounds. Plants using genuinely skilled cover see their repeat failure rate fall, because every incident, whenever it occurs, feeds the improvement loop. Plants using warm body cover stay on the breakdown treadmill and never quite understand why.

    Lesson Three: Continuity Turns Cover Into Capability

    Beverage plants that use the same covering tradespeople repeatedly report something interesting: after a few months, the contractors stop feeling like contractors. They know the plant’s fault history, they anticipate the summer failure modes on the refrigeration and glycol systems, and they contribute observations to toolbox talks. The lesson is to treat cover as a relationship, not a transaction. Request good people by name, invest in their site knowledge, and work with a provider who can actually deliver continuity because they retain their trades year round.

    Continuity also derisks the scary shifts. When the covering electrician on Saturday night has worked your site twenty times, the difference between them and a permanent employee, from a risk perspective, is close to nil.

    Lesson Four: The Provider’s Depth Is Your Depth

    Sooner or later, a covered shift meets a problem bigger than one person: a control system failure with no obvious cause, a mechanical breakage needing a machined part, a safety system fault that must not be guessed at. What happens next depends entirely on what stands behind the person on your floor. If the answer is a recruitment office that opens at 8:30am, the shift is on its own. If the answer is an engineering business with automation engineers on call, TUV certified functional safety expertise, and a workshop with CNC machining and fabrication capability, the shift has depth behind it, at 2am as at 2pm.

    This is the structural advantage of sourcing cover from a working engineering firm. BevTech, family owned with more than 25 years in FMCG and beverage manufacturing, supports Queensland plants with exactly that stack: the covering tradesperson on the floor, engineers who program Allen Bradley and Siemens PLC systems behind them, and a workshop that can turn, mill or fabricate an emergency part behind that. Its project history on beverage sites, from refrigeration PLC control systems managing beer tank temperatures to hot water rinse CIP systems for can seamers and can inverter block systems for high speed lines, means the systems your cover is protecting are systems the business builds and repairs every week.

    Lesson Four and a Half: Bring the Operators With You

    A quieter lesson from the production floor is that shift cover works best when operators are treated as part of the system rather than bystanders. Operators are the first sensors in any breakdown; they hear the bearing before it fails and see the jam before the alarm. Introduce covering tradespeople to the operating crew at shift start, make sure operators know the contractor is there for them, and encourage the early quiet word about a machine behaving oddly. Plants that do this find their covering trades intervene earlier, often converting a would be breakdown into a five minute adjustment during a scheduled stop. Plants that skip it find faults are reported late and context is lost, because operators hesitate to bother a stranger. The habit costs one minute at shift handover. Over a peak season it is worth hours of uptime, and it makes the covering tradesperson feel like part of the crew, which shows in the standard of their work.

    Lesson Five: Measure It Like a Reliability Initiative

    Finally, put numbers on it. Track downtime hours by shift, and separately track which shifts ran with full trades cover. Most plants that do this find the uncovered and thinly covered shifts carry a disproportionate share of downtime, and the case for structured cover writes itself. Then hold the cover arrangement to the same standard: response times, incidents resolved independently, repeat failure contribution, and feedback from your permanent team. Reliable shift cover should visibly move your numbers. If it does not, you have a staffing patch, not a reliability tool, and it is time to change providers.

    Putting the Lessons to Work

    The path from here is short. Audit your roster for structurally uncovered shifts, quantify what those shifts have cost over the past six months, and establish a relationship with a specialist provider before the next peak season locks up the market. BevTech provides skilled, continuous shift cover to FMCG and beverage manufacturers across Brisbane and Queensland, with industrial electricians, fitters, turners and automation technicians backed by a 24/7 engineering business trusted by some of the largest manufacturing companies in Australia. Start the conversation through the contact form at bevtech.com.au, and turn your quietest shifts into your most reliable ones.

@Fd2X@HoSi10178
Shutdown Checklist
Bevtech fmcg beverage shutdown planning checklist glass.webp0000

Get Your FMCG & Beverage Plant Shutdown Planning Checklist

We wont spam you :) or share your details.
We will send you an email with the PDF checklist.