When the Power Goes Wrong on a Production Floor

An electrical emergency in a factory is different from one in an office or a home. There is product in tanks and on lines, refrigeration that cannot stay off for long, cleaning cycles part way through and machinery that may not be safe to restart without checks. The decisions made in the first hour largely determine whether the event costs a few hours or a few days.

This guide is for plant and shift managers in Brisbane and South East Queensland. It covers what to do first, how to get the right emergency electrician moving quickly, what the law requires you to report and how to prepare so that the next event is shorter.

First: People

If anyone has received an electric shock, or may still be in contact with a live part, do not touch them. Isolate the supply if you can do so safely, call triple zero and begin first aid once the person is clear of the electrical source. Anyone who has received a shock should be medically assessed even if they feel well, because effects can be delayed.

If there is fire, smoke or a burning smell from electrical equipment, evacuate the area and call triple zero. Do not use water on electrical equipment.

Keep people away from the affected equipment. Do not open switchboard doors to look. A fault inside a switchboard can release a great deal of energy, and an unqualified person in front of an open panel is in the worst possible place.

Second: Work Out What Has Actually Failed

From a safe distance, establish the extent of the problem. The answer directs everything that follows.

The whole site is off. Check whether neighbouring premises have power. If they do not, the fault is probably on the network and the call is to your electricity distributor, which in South East Queensland is Energex. If neighbours have power, the problem is likely your own main switch or incoming equipment.

Part of the site is off. A section of the plant or a group of machines without power points to a tripped breaker or blown fuse on a sub main or distribution board.

One machine is off. This is a machine fault and the most common case.

Things are behaving strangely. Motors humming and not starting, lights dim in one area or equipment running hot suggests a lost phase. Stop affected motors, because a motor running on two phases can burn out quickly.

Third: Do Not Keep Resetting

A circuit breaker that trips has done its job. It is protecting cable and equipment from damage. Resetting it once, after a visual check for anything obvious, is reasonable. Resetting it repeatedly is not. Each attempt closes the supply onto a fault, and each one can do more damage to the equipment and to the breaker itself.

If it trips again, leave it off and call an electrician. The same applies to drives and overloads that keep tripping.

Fourth: Protect the Product

While help is on the way, the production team can limit the loss. The priorities in a beverage or food plant are usually these.

Refrigeration and temperature control. Find out how long tanks and cold rooms can hold temperature. Keep doors shut. If glycol or refrigeration plant is down, this becomes the clock that matters.

Cleaning cycles. A CIP cycle interrupted part way through may have left chemical in the line. Make sure nobody restarts production on that circuit until it has been checked and the cycle completed.

Product in process. Decide what on the line can be recovered and what must be held for quality review.

Controlled restart. When power returns, do not let everything start at once. Bring equipment up in sequence so that the starting load is spread and so that each machine is checked as it comes back.

Fifth: Make the Call Count

An emergency electrician can prepare on the way if you give them the right information. Have the following ready.

Which area and which machine is affected. What was happening when it failed. Any alarm messages or fault codes, exactly as displayed. Whether a breaker has tripped and which one. What has been tried already. Whether anyone was hurt. The control platform on the machine, such as Allen Bradley or Siemens. Who will meet them at the gate and what induction they need.

Send someone to find the electrical drawings for the affected equipment and the latest software backup. Having them on a bench when the electrician arrives can save an hour.

What You May Be Required to Report

Some electrical events must be notified to Queensland’s Electrical Safety Office by the business concerned. The Electrical Safety Act 2002 defines two categories.

A serious electrical incident includes a person being killed by electricity, a person receiving a shock or injury from electricity that is treated by or under the supervision of a doctor, and a person receiving a shock or injury from electricity at high voltage whether or not treatment is given.

A dangerous electrical event includes significant property damage caused by electricity or by a fire originating from electricity, as well as unlicensed or unsafe electrical work.

Where a death is involved, notification must be immediate. In other cases notify promptly by phone and follow up with the written incident notification form. Keep your records of the incident for at least five years.

There is a second obligation that is easy to breach under pressure. It is unlawful to interfere with the scene of a notifiable incident without the permission of an inspector or a police officer, except where that is necessary to save life, relieve suffering or prevent injury or property damage. Make the area safe, then leave it as it is until you have been told you can proceed. Repairs to get production going do not come first.

After the Power Is Back

Getting running again is not the end of the job. Ask the electrician what failed and why, and get the answer in writing. A breaker that tripped because a motor failed is a different matter from one that tripped because the switchboard is overloaded. If the cause was not found, treat the event as unfinished and schedule a proper investigation.

Then record it: time, extent, cause, what was done and how long each stage took. The stages that took longest are the ones to fix before next time.

Preparing Before It Happens

Plants that recover quickly have usually done a few simple things in advance.

A current single line diagram of the site, displayed in the main switch room and held in the maintenance office. Switchboards and breakers labelled to show what they feed. An emergency contact list with the distributor’s fault line and your electrical provider’s after hours number, posted where the night shift can see it. Drawings and software backups stored where they can be found without the day shift. Critical spares identified and on the shelf. A restart sequence written down. And an agreed arrangement with an industrial electrician who already knows the site, so that the first call is not also the first introduction.

Emergency Electrical Support From BevTech

BevTech is a family owned engineering business in Richlands, Brisbane, with more than 25 years in beverage and FMCG manufacturing. Our industrial electricians provide 24/7 breakdown support and shift coverage across Brisbane and South East Queensland, with fast, methodical diagnosis of electrical and control faults on Allen Bradley and Siemens systems. Our mechanical trades and machine shop are part of the same business, so a failure that turns out to need a part made is still handled by one team.

The best time to set up emergency cover is before you need it. To talk through an arrangement for your plant, use the contact form at simonb307.sg-host.com/contact.

This article is a general guide current as at October 2026 and is not a substitute for your site emergency procedures. In a life threatening emergency call triple zero.

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *

@Fd2X@HoSi10178
Shutdown Checklist
Bevtech fmcg beverage shutdown planning checklist glass.webp0000

Get Your FMCG & Beverage Plant Shutdown Planning Checklist

We wont spam you :) or share your details.
We will send you an email with the PDF checklist.