The Piece of Paper Most Plants Never Ask For
A contractor installs a new machine supply, modifies a switchboard or replaces a drive. The line runs, the invoice arrives and everyone moves on. Months later an auditor, an insurer or an investigator asks a simple question: where is the certificate for that work? In many plants nobody knows, because nobody realised one was owed.
In Queensland, a licensed electrical contractor must certify electrical work once it has been tested. Knowing what you are entitled to receive, and keeping it, is one of the cheapest compliance habits a manufacturer can adopt. This guide explains the two certificates, what each must contain and how to build them into the way your site closes out electrical work.
Two Certificates, Two Kinds of Work
People search for an electrical compliance certificate or a certificate of compliance. Queensland’s rules actually provide for two documents, and which one applies depends on what was worked on.
Certificate of testing and compliance. Issued for electrical installation work. In a plant that means the fixed wiring and associated equipment: switchboards, sub mains, final circuits, socket outlets, and the supply to a machine.
Certificate of testing and safety. Issued for work on electrical equipment, as distinct from the installation that supplies it.
A single project can involve both. If it is not obvious which applies to a job on your site, ask the contractor before work starts which certificate they will issue and why. A contractor who does this work regularly will answer without hesitation.
What Each Certificate Must Say
Both certificates must include the name and address of the person for whom the work was performed, details of the equipment or installation that was tested, the date of testing and the electrical contractor licence number.
They then differ in what is certified. A certificate of testing and safety states that the electrical equipment has been tested to ensure it is electrically safe. A certificate of testing and compliance states that the electrical installation has been tested to ensure it is electrically safe and is in accordance with the requirements of the wiring rules, which means AS/NZS 3000.
The wording matters. The contractor is certifying that the work was tested, not only that it was carried out. A certificate with a vague description, such as electrical works as quoted, is of limited use to you later. Ask for a description specific enough that someone else could identify the circuit or equipment.
Who Issues It, and Who Receives It
The certificate is issued by the electrical contractor that performed the work, or by workers acting under that contractor’s licence. It goes to the person for whom the work was done, which in practice is the business that engaged the contractor and will receive the invoice.
If your plant engages a principal contractor for a project and the electrical work is subcontracted, be clear in the contract about how certificates will reach you. They are frequently issued to the principal contractor and never passed on.
When You Should Receive It
The contractor must provide the certificate as soon as possible after completing the work. There is no reason for it to trail the job by weeks. A sensible practice is to treat the certificate as part of practical completion: no certificate, no sign off, and the invoice waits.
The contractor must also keep a copy for at least five years. That is useful if yours goes missing, but you should not rely on it. Contractors change systems, change hands and close.

The Regulation Changed Its Numbering in 2026
These requirements sit under the Electrical Safety Act 2002 and its regulation. The Electrical Safety Regulation 2026 commenced on 1 September 2026 and replaced the Electrical Safety Regulation 2013. According to the Electrical Safety Office, the new regulation does not introduce new policy or regulatory obligations. It does restructure the document, and every section number has changed.
The practical consequence is in your paperwork. Site procedures, contractor agreements, permit forms and older guidance that quote section numbers from the 2013 regulation are now pointing at the wrong place. The obligations are the same, but the references should be updated when documents next come up for review.
What a Certificate Does Not Cover
A certificate confirms that electrical work has been tested and is electrically safe. It is not a certification of the whole machine or the whole site, and it does not replace several other things a plant needs.
Machine safety validation. Proof that guards, interlocks, light curtains and emergency stops perform their safety functions is a separate exercise with its own records.
Test results. The certificate says testing was done. The readings themselves, such as insulation resistance and earth continuity, are worth asking for.
Drawings. Nothing in the certificate updates your schematics.
Software. Changes to PLC, HMI or drive settings are not captured.
Pre-existing conditions. The certificate relates to the work performed, not to everything else in the switchboard.
A Handover Pack Worth Asking For
For anything beyond a minor repair, ask for the following as a set.
The certificate of testing and compliance or certificate of testing and safety, with a specific description of the work. Test results. New or updated electrical drawings. Backups of any PLC, HMI or drive configuration that was changed. Safety validation records where a safety function was touched. Manuals and settings for new equipment. A list of anything the contractor noticed that needs attention.
Put this list in your purchase order or contractor agreement. It costs a good contractor very little to provide, because they produce most of it anyway. A contractor who resists is telling you something.
Where to Keep Them
Certificates are only useful if they can be found. File them against the asset or the area of the plant, not against the supplier or the invoice number, because the question you will be asked later is what was done to this switchboard, not what did we buy from that contractor in March.
Keep a scanned copy with your maintenance records and another off site. Record the certificate number or date in the work order. When equipment is sold or a site is handed back to a landlord, the file goes with it.
When Your Own Electricians Do the Work
The certificate obligations described here apply to licensed electrical contractors performing work for others. Many plants also employ their own electricians. Work done in-house must still be tested and electrically safe, and the record keeping expected of an employer is a separate matter. If your site has a maintenance team doing electrical work, confirm with the Electrical Safety Office what records you should be keeping, and consider adopting the same handover pack internally.
A Simple Check for Your Site
Pick the last three pieces of electrical work a contractor did on your site. For each, find the certificate. If you can produce all three in ten minutes, your system works. If you cannot, the fix is a line in your contractor procedure and a folder, and it is worth doing before someone else asks.
How BevTech Closes Out Electrical Work
BevTech is a family owned engineering business in Richlands, Brisbane, with more than 25 years in beverage and FMCG manufacturing. Our industrial electricians carry out installations to AS/NZS 3000, machine installation and commissioning, and safety system upgrades across Brisbane and South East Queensland. We take work from design through installation, testing and handover, with full electrical design drawings for new work and as-built updates for changes.
If you would like help getting the documentation on your site back in order, including an electrical audit to establish what you have, use the contact form at simonb307.sg-host.com/contact.
This article is a general guide current as at October 2026 and is not legal advice. Confirm the requirements for your own circumstances with the Electrical Safety Office.